[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109623,783,1,"单选题","（2020年真题）某工程约定采用价格指数法调整合同价款，承包人根据约定提供的数据如下表。本期完成合同价款为45万元，其中已按现行价格计算的计日工价款为5万元。本期应调整的合同价款差额为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","-2.85",false,{"key":16,"text":17,"correct":14},"B","-2.54",{"key":19,"text":20,"correct":21},"C","2.77",true,{"key":23,"text":24,"correct":14},"D","3.12","P167-171 本期应调整的合同价款差额=（45-5）*（0.25+0.30*120%\u002F110%+0.25*123%\u002F112%+0.2*125%\u002F115%-1）=2.77万元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]