[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109622,783,1,"单选题","（2020年真题）某工程施工至2020年6月底，经统计分析：已完工作预算投资2500万元，已完工作实际投资2800万元，计划工作预算投资2600万元。该工程此时的投资绩效指数为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.89",true,{"key":16,"text":17,"correct":18},"B","0.96",false,{"key":20,"text":21,"correct":18},"C","1.04",{"key":23,"text":24,"correct":18},"D","1.12","P208-213 投资绩效指数（CPI）=已完工作预算投资（BCWP） \u002F已完工作实际投资（ACWP）=2500\u002F2800=0.89",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]