[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109621":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109621,783,1,"单选题","（2020年真题）根据《建设工程施工合同（示范文本）》，除专用合同条款另有约定外，承包人向监理人报送上月20日至当月19日已完成工程量的时间为每月（ ）日。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":21},"C","25",true,{"key":23,"text":24,"correct":14},"D","28","P160-162 承包人应于每月25日向监理人报送上月20日至当月19日已完成的工程量报告，并附具进度付款申请单、已完成工程量报表和有关资料。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]