[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109618,783,1,"单选题","（2019年真题）某工程在施工过程中，因不可抗力造成如下损失：（1）在建工程损失10万元；（2）承包人受伤人员医药费和补偿金2万元；（3）施工机具损坏损失1万元；（4）工程清理和修复费用0.5万元。承包人及时向项目监理机构提出了索赔申请，共索赔13.5万元。根据《建设工程工程量清单计价规范》，项目监理机构应批准的索赔金额为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10.0",false,{"key":16,"text":17,"correct":18},"B","10.5",true,{"key":20,"text":21,"correct":14},"C","12.5",{"key":23,"text":24,"correct":14},"D","13.5","本题考查的是不可抗力。索赔金额＝在建工程损失10万元＋工程清理和修复费用0.5万元＝10.5万元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]