[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109615":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109615,783,1,"单选题","（2019年真题）承包人在施工中遇到了一个有经验的承包人也难以预测的不利物质条件，导致承包人成本增加和工期延误，则承包人可索赔（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","增加的成本、延误的工期和相应利润",false,{"key":16,"text":17,"correct":14},"B","延误的工期，不能索赔增加的成本和相应利润",{"key":19,"text":20,"correct":14},"C","增加的成本，不能索赔延误的工期和相应利润",{"key":22,"text":23,"correct":24},"D","增加的成本和延误的工期，不能索赔相应利润",true,"本题考查的是索赔的主要类型。承包人遇到不利物质条件，可索赔费用+工期。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]