[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109613,783,1,"单选题","（2018年真题）某工程施工至2018年3月底，经统计分析：已完工作预算投资580万元，已完工作实际投资570万元，计划工作预算投资600万元，该工程此时的进度偏差为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-30",false,{"key":16,"text":17,"correct":18},"B","-20",true,{"key":20,"text":21,"correct":14},"C","-10",{"key":23,"text":24,"correct":14},"D","10","本题考查的是赢得值法。进度偏差=已完工作预算投资-计划工作预算投资=580-600=-20（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]