[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109611,783,1,"单选题","（2016年真题）下列事件中，需要进行现场签证的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","合同范围以内零星工程的确认",false,{"key":16,"text":17,"correct":14},"B","修改施工方案引起工程量增减的确认",{"key":19,"text":20,"correct":14},"C","承包人原因导致设备窝工损失的确认",{"key":22,"text":23,"correct":24},"D","合同范围以外新增工程的确认",true,"本题考查的是计日工。任一计日工项目持续进行时，承包人应在该项工作实施结束后的24h内向发包人提交有计日工记录汇总的现场签证报告一式三份。发包人在收到承包人提交现场签证报告后的2天内予以确认并将其中一份返还给承包人，作为计日工计价和支付的依据。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]