[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109606":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109606,783,1,"单选题","（2015年真题）某工程基础底板的设计厚度为1m，承包人根据以往的施工经验，认为该设计有问题，未经项目监理机构同意，即按1.2m厚度施工。专业监理工程师在计量时，对承包人多完成的工程量应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","予以计量",false,{"key":16,"text":17,"correct":18},"B","不予计量",true,{"key":20,"text":21,"correct":14},"C","计量一半",{"key":23,"text":24,"correct":14},"D","由发包人与承包人协商处理","本题考查的是工程计量的依据。监理工程师对承包人超出设计图纸要求增加的工程量和自身原因造成返工的工程量，不予计量。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]