[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109602,783,1,"单选题","下列关于赢得值法说法正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","已完工作预算投资(BCWP)=计划工作量×预算单价",false,{"key":16,"text":17,"correct":14},"B","计划工作预算投资(BCWS)=已完成工作量×预算单价",{"key":19,"text":20,"correct":21},"C","已完工作实际投资(ACWP)=已完成工作量×实际单价",true,{"key":23,"text":24,"correct":14},"D","投资偏差(CV)=已完工作实际投资(ACWP)-已完工作预算投资(BCWP)","2020版教材P208-213 已完工作预算投资(BCW2020版教材P)=已完成工作量×预算单价； 计划工作预算投资(BCWS)=计划工作量×预算单价； 已完工作实际投资(ACW2020版教材P)=已完成工作量×实际单价； 投资偏差(CV)=已完工作预算投资(BCW2020版教材P)-已完工作实际投资(ACW2020版教材P)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]