[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109601,783,1,"单选题","下列关于竣工结算编制说法正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","措施项目中的单价项目如发生调整的按已标价工程量清单的综合单价计算",false,{"key":16,"text":17,"correct":14},"B","安全文明施工费由施工单位根据自身施工水平计算",{"key":19,"text":20,"correct":21},"C","措施项目中的总价项目应依据已标价工程量清单的项目和金额计算",true,{"key":23,"text":24,"correct":14},"D","分部分项工程中的单价项目如发生调整的按已标价工程量清单的综合单价计算","2020版教材P201-202 措施项目中的总价项目应依据已标价工程量清单的项目和金额计算；发生调整的，应以发承包双方确认调整的金额计算，其中安全文明施工费应按国家或省级、行业建设主管部门的规定计算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]