[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109600":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109600,783,1,"单选题","下列关于安全文明施工费的说法中，叙述正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人应在工程开工后的28天内预付不低于当年施工进度计划的安全文明施工费总额的50％",false,{"key":16,"text":17,"correct":14},"B","发包人在付款期满后的7天内仍未支付的，若发生安全事故，承包人应承担全部责任",{"key":19,"text":20,"correct":14},"C","承包人对安全文明施工费应专款专用.在财务账目中单独列项备查，可挪作他用",{"key":22,"text":23,"correct":24},"D","发包人没有按时支付安全文明施工费的，承包人可催告发包人支付",true,"2020版教材P195 发包人应在工程开工后的28 天内预付不低于当年施工进度计划的安全文明施工费总额的60%。其余部分按照提前安排的原则进行分解，与进度款同期支付。发包人没有按时支付安全文明施工费的，承包人可催告发包人支付；发包人在付款期满后的7 天内仍未支付的，若发生安全事故，发包人应承担相应责任。 承包人对安全文明施工费应专款专用，在财务账目中单独列项备查，不得挪作他用，否则发包人有权要求其限期改正；逾期未改正的，造成的损失和延误的工期由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]