[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109598,783,1,"单选题","某工程施工至2013年12月底，经分析，已完工作预算投资为100万元，已完工作实际投资为115万元，计划工作预算投资为110万元。则该工程的进度偏差为（）。?",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","超前15万元",false,{"key":16,"text":17,"correct":14},"B","延误15万元",{"key":19,"text":20,"correct":14},"C","超前10万元",{"key":22,"text":23,"correct":24},"D","延误10万元",true,"2020版教材P208-213 进度偏差=已完工作预算投资- 计划工作预算投资，100-110=-10万，即延误10万。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]