[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109596":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109596,783,1,"单选题","采用清单计价的分部分项工程，招标控制价的综合单价为320元，投标报价的综合单价为265元，该工程投标报价下浮率为5%，结算时，该分项工程工程量比清单量增加了18%，且合同未确定综合单价调整方法，则综合单价的处理方法是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","上浮18%",false,{"key":16,"text":17,"correct":14},"B","下调5%",{"key":19,"text":20,"correct":14},"C","调整为292.5%",{"key":22,"text":23,"correct":24},"D","可不调整",true,"2020版教材P164-166 上限值320×1.15=368，下限320×0.85×0.95=258.4。因为投标报价的综合单价为265元，位于上、下限值之间，故不调。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]