[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109591,783,1,"单选题","某工程受异常大雪影响，导致承包商工期延长，根据《标准施工招标文件》的条款，承包商有权要求的索赔是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","费用，但不包括工期",false,{"key":16,"text":17,"correct":14},"B","工期、费用，但不包括利润",{"key":19,"text":20,"correct":21},"C","工期，但不包括费用",true,{"key":23,"text":24,"correct":14},"D","工期、费用和利润","2020教材P178-184",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]