[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109590,783,1,"单选题","对涉及工程设计文件修改的工程变更，应由（ ）转交原设计单位修改工程设计文件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","质量监督机构",{"key":23,"text":24,"correct":14},"D","监理工程师","2020教材P174-175 总监理工程师组织专业监理工程师审查承包人提出的工程变更申请，提出审查意见。对涉及工程设计文件修改的工程变更，应由发包人转交原设计单位修改工程设计文件。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]