[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109588":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109588,783,1,"单选题","某混凝土结构工程，工程量清单中估计工程量为50000m3，合同规定混凝土结构工程综合单价为600元／m3，并且当实际工程量超过估计工程量15％时，超过部分应调整单价，单价调为550元／m3。工程结束时承包人实际完成混凝土结构工程量为65000 m3，则该项工程结算款为（）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3862.5",true,{"key":16,"text":17,"correct":18},"B","3850",false,{"key":20,"text":21,"correct":18},"C","3737.5",{"key":23,"text":24,"correct":18},"D","3575","2020教材P175-178 工程结算款=50000×(1+15％)×600+[65000-50000×(1+15％)]×550=3862.5(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]