[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109586,783,1,"单选题","某工程在施工过程中，因不可抗力造成损失。承包人及时向项目监理机构提出了索赔申请，并附有相关证明材料，其中在建工程损失30万元，承包人施工机械损失10万元，承包人施工人员窝工损失3．5万元，故监理机构应批准的补偿金额是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30万元",true,{"key":16,"text":17,"correct":18},"B","33.5万元",false,{"key":20,"text":21,"correct":18},"C","40万元",{"key":23,"text":24,"correct":18},"D","43.5万元","2020教材P178-184 不可抗力带来的建筑实体本身损失，即30万元，发包人予以费用补偿，而承包人自身的机械、窝工，承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]