[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109584":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109584,783,1,"单选题","单价合同计量中，监理人应在收到承包人提交的工程量报告后（）内完成对承包人提交的工程量报表的审核并报送发包人，以确定当月实际完成的工程量。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","24h",false,{"key":16,"text":17,"correct":14},"B","3天",{"key":19,"text":20,"correct":21},"C","7天",true,{"key":23,"text":24,"correct":14},"D","14天","2020教材P160-162 监理人应在收到承包人提交的工程量报告后7 天内完成对承包人提交的工程量报表的审核并报送发包人，以确定当月实际完成的工程量。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]