[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109583":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109583,783,1,"单选题","一般而言，在不影响施工总工期的前提下，有利于节约发包人的建设资金贷款利息的工作安排方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","所有工作均按最早开始时间安排",false,{"key":16,"text":17,"correct":18},"B","所有工作均按最迟开始时间安排",true,{"key":20,"text":21,"correct":14},"C","早期工作按最早时间安排，后期工作按最迟时间安排",{"key":23,"text":24,"correct":14},"D","早期工作按最迟时间安排，后期工作按最早时间安排","2020教材P155-159 一般而言，所有工作都按最迟开始时间开始，对节约发包人的建设资金贷款利息是有利的，但同时，也降低了项目按期竣工的保证率。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]