[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109581,783,1,"单选题","某混凝土工程，9月份计划工作量为5000m3，预算单价为400元\u002Fm3；而9月份实际完成工作量为4000m3，实际单价为450元\u002Fm3，则该工程9月份的进度绩效指数为( )万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1.125",false,{"key":16,"text":17,"correct":14},"B","0.89",{"key":19,"text":20,"correct":21},"C","0.8",true,{"key":23,"text":24,"correct":14},"D","1.25","2020教材P208-213 进度绩效指标=已完工作预算费\u002F计划工作预算费=（4000×400）\u002F（5000×400）=0.8",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]