[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109580,783,1,"单选题","某工程的招标控制价为800万元，中标人的投标报价为780万元，施工图预算造价为790万元，则承包人的报价浮动率为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.04％",false,{"key":16,"text":17,"correct":18},"B","2.50％",true,{"key":20,"text":21,"correct":14},"C","2.88％",{"key":23,"text":24,"correct":14},"D","2.96％","2020教材P175-178 根据招标工程承包人报价浮动率的计算公式，则本工程的报价浮动率L=(1-中标价／招标控制价)×100％=(1-780／800)×100％=2．50％。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]