[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109579,783,1,"单选题","某承包人承包某项工程项目，发承包双方的合同中约定，建安工程造价为2000万元，建筑材料及设备费占施工产值的比重60％，工程预付款为建安工程造价的20％。则该项工程的预付款和起扣点分别是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","400万元；1200万元",false,{"key":16,"text":17,"correct":18},"B","400万元；1333万元",true,{"key":20,"text":21,"correct":14},"C","400万元；800万元",{"key":23,"text":24,"correct":14},"D","1200万元；0万元","2020教材P194-195 预付款=建安工程造价×20％=400万元；起扣点T=2020教材P-M／N=2000-400／60％=1333．33万元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]