[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109577,783,1,"单选题","赢得值是指( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计划工作预算投资",false,{"key":16,"text":17,"correct":14},"B","已完工作实际投资",{"key":19,"text":20,"correct":21},"C","已完工作预算投资",true,{"key":23,"text":24,"correct":14},"D","计划工作实际投资","2020教材P208-213 已完工作预算投资为BCW2020教材P ，是指在某一时间已经完成的工作(或部分工作) ，以批准认可的预算为标准所需要的资金总额，由于发包人正是根据这个值为承包人完成的工作量支付相应的投资，也就是承包人获得(挣得)的金额，统称赢得值或挣值。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]