[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109572":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109572,783,1,"单选题","2014年7月，某工程按基准日期价格完成的7月份工程款为1500万元。由于发生物价变化，发承包双方协议采用价格指数进行价格调整，其中工程款的定值权重为0．2，相关成本要素中，水泥的价格指数上升了20％，水泥的费用占合同调值部分的40％，其他成本要素的价格均未发生变化。2014年7月应调整的合同价的差额为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","96",true,{"key":16,"text":17,"correct":18},"B","126",false,{"key":20,"text":21,"correct":18},"C","1596",{"key":23,"text":24,"correct":18},"D","1626","2020教材P167-171 根据调值公式进行计算如下： 1500×[(0．2+0．8×0．4 ×120％／100％+0．8×0．6)-1]=96(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]