[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109571,783,1,"单选题","某施工合同约定，人员窝工补贴为15元／工日。在基础工程施工期间，因罕见暴雨导致基坑淹水而停工2天，人员窝工20个工日；在主体工程施工期间，因重大公共活动、政府通知停工2天，人员窝工30个工日。为此，承包人可向业主索赔工期和费用分别为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4天，750元",false,{"key":16,"text":17,"correct":14},"B","4天，450元",{"key":19,"text":20,"correct":21},"C","4天，0元",true,{"key":23,"text":24,"correct":14},"D","2天，0元","2020教材P178-184 本题考查的是索赔费用的计算。 根据《标准施工招标文件》的条款，因罕见暴雨导致基坑淹水和因重大公共活动、政府通知的停工虽属非承包人原因，但也不是发包人的原因。发包人可以予以工期延长，但不会予以费用及利润的索赔。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]