[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109567,783,1,"单选题","某工程基础施工中，施工人员发现大型文物古迹，因此工程暂停，承包人做了相应的保护措施，根据《标准施工招标文件》的条款，承包商有权索赔（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","费用，但不包括工期和利润",false,{"key":16,"text":17,"correct":14},"B","费用和利润，但不包括工期",{"key":19,"text":20,"correct":21},"C","工期和费用，但不包括利润",true,{"key":23,"text":24,"correct":14},"D","工期、费用和利润","2020教材P178-184 在施工过程中，承包商遇到了文物、古迹，根据《标准施工招标文件》的条款，承包商有权向发包人索赔，要求延长工期和费用的补偿，但不包括利润。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]