[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109564":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109564,783,1,"单选题","某工程由于承包人原因未在约定的工期内竣工。若该工程在原约定竣工日期后继续施工，则采用价格指数调整其价格差额时，现行价格指数应采用( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","原约定竣工日期的价格指数",false,{"key":16,"text":17,"correct":14},"B","实际竣工日期的价格指数",{"key":19,"text":20,"correct":21},"C","原约定竣工日期和实际竣工日期价格指数中较低的一个",true,{"key":23,"text":24,"correct":14},"D","实际竣工日期前42天的价格指数","2020教材P167-171 由于承包人原因未在约定的工期内竣工的，则对原约定竣工日期后继续施工的工程，在使用价格调整公式时，应采用原约定竣工日期与实际竣工日期的两个价格指数中较低的一个作为现行价格指数。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]