[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109563,783,1,"单选题","某包工包料工程合同总金额为1000万元，工程预付款的比例为20%，主要材料构件所占比重为50%，按起扣点基本计算工程，则工程累计完成至( )万元时应开始扣回工程预付款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","200",false,{"key":16,"text":17,"correct":18},"B","600",true,{"key":20,"text":21,"correct":14},"C","400",{"key":23,"text":24,"correct":14},"D","800","2020教材P194-195 起扣点T=2020教材P-M／N=1000-1000*20%\u002F50%=600万元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]