[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109561":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109561,783,1,"单选题","投资偏差结果为正，进度偏差为负表示( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","投资节约，进度延误",true,{"key":16,"text":17,"correct":18},"B","投资节约，进度提前",false,{"key":20,"text":21,"correct":18},"C","投资超支，进度延误",{"key":23,"text":24,"correct":18},"D","投资超支，进度提前","2020教材P208-213 当进度偏差SV 为负值时，表示进度延误，实际进度落后于计划进度;当进度偏差SV 为正值时，表示进度提前，实际进度快于计划进度。 当投资偏差CV 为负值时，表示项目运行超出预算投资;当投资偏差CV 为正值时，表示项目运行节支，实际投资没有超出预算投资。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]