[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109560":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109560,783,1,"单选题","某施工企业进行土方开挖工程，按合同约定3月份的计划工作量为2400ｍ3，计划单价是12元\u002Fｍ3；到月底检查时，确认承包商完成的工程量为2000ｍ3，实际单价为15元\u002Fｍ3 。则该工程的进度偏差（SV）和进度绩效指数（SPI）分别为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.6万元；0.80",false,{"key":16,"text":17,"correct":14},"B","-0.6万元；0.83",{"key":19,"text":20,"correct":21},"C","-0.48万元；0.83",true,{"key":23,"text":24,"correct":14},"D","0.48万元；0.80","本题考查的是赢得值法。进度偏差=已完工作预算费用－计划工作预算费用=（2000-2400）×12=-4800元；进度绩效指数=已完工作预算费用\u002F计划工作预算费用=2000×12\u002F（2400×12）=0.83。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]