[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109559,783,1,"单选题","某分项工程月计划完成工程量为3200m2，计划单价为15元\u002Fm2，月底承包商实际完成工程量为2800m2，实际单价为20元\u002Fm2，则该工程当月的计划工作预算投资（BCWS）为（ ）元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","42000",false,{"key":16,"text":17,"correct":18},"B","48000",true,{"key":20,"text":21,"correct":14},"C","56000",{"key":23,"text":24,"correct":14},"D","64000","本题考查的是赢得值法。BCWS=计划工作量×预算单价=3200×15=48000元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]