[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109550,783,1,"单选题","根据《建设工程工程量清单计价规范》，发包人应在工程开工后的28 天内预付不低于当年施工进度计划的安全文明施工费总额的()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","30%",false,{"key":16,"text":17,"correct":14},"B","40%",{"key":19,"text":20,"correct":14},"C","50%",{"key":22,"text":23,"correct":24},"D","60%",true,"鉴于安全文明施工的措施具有前瞻性，必须在施工前予以保证。 发包人应在工程开工后的28 天内预付不低于当年施工进度计划的安全文明施工费总额的60%，其余部分按照提前安排的原则进行分解，与进度款同期支付。发包人没有按时支付安全文明施工费的，承包人可催告发包人支付；发包人在付款期满后的7 天内仍未支付的，若发生安全事故，发包人应承担相应责任。 承包人对安全文明施工费应专款专用，在财务账目中单独列项备查，不得挪作他用，否则发包人有权要求其限期改正；逾期未改正的，造成的损失和延误的工期由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]