[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109549":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109549,783,1,"单选题","发包人应当开始支付不低于当年施工进度计划的安全文明施工费总额60%的期限是工程开工后的()天内。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":14},"C","21",{"key":22,"text":23,"correct":24},"D","28",true,"鉴于安全文明施工的措施具有前瞻性，必须在施工前予以保证。 发包人应在工程开工后的28 天内预付不低于当年施工进度计划的安全文明施工费总额的60%，其余部分按照提前安排的原则进行分解，与进度款同期支付。发包人没有按时支付安全文明施工费的，承包人可催告发包人支付；发包人在付款期满后的7 天内仍未支付的，若发生安全事故，发包人应承担相应责任。 承包人对安全文明施工费应专款专用，在财务账目中单独列项备查，不得挪作他用，否则发包人有权要求其限期改正；逾期未改正的，造成的损失和延误的工期由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]