[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109547":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109547,783,1,"单选题","某工程施工至2017 年12 月底,经统计分析:已完工作作预算投资480 万元,已完工作实际投资510 万元,计划工作预算投资450 万元,该工程此时的投资绩效指数为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.88",false,{"key":16,"text":17,"correct":18},"B","0.94",true,{"key":20,"text":21,"correct":14},"C","1.06",{"key":23,"text":24,"correct":14},"D","1.07","投资绩效指数=已完工作预算投资\u002F已完工作实际投资=480\u002F510=0.94",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]