[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109543":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109543,783,1,"单选题","关于工程量清单计价方式下竣工结算的编制原则，下列说法中正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","措施项目费按双方确认的工程量乘以已标价工程量清单的综合单价计算",false,{"key":16,"text":17,"correct":14},"B","总承包服务费按已标价工程量清单的金额计算，不应调整",{"key":19,"text":20,"correct":14},"C","暂列金额应减去工程价款调整的金额，余额归承包人",{"key":22,"text":23,"correct":24},"D","工程实施过程中发承包双方已经确认的工程计量结果和合同价款，应直接进入结算",true,"本题考查的是竣工结算编制。选项A，总价措施项目：依据合同约定的项目和金额计算；安全文明施工费必须按规定计算；选项B，可以进行调整；选项C，如有余额归发包人。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]