[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109540,783,1,"单选题","发包人应在签发竣工结算支付证书后的( )天内，按照竣工结算支付证书列明的金额向承包人支付结算款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","28","2020教材P203-204 发包人应在收到承包人提交竣工结算款支付申请后7 天内予以核实，向承包人签发竣工结算支付证书，并在签发竣工结算支付证书后的14 天内，按照竣工结算支付证书列明的金额向承包人支付结算款。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]