[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109539,783,1,"单选题","发包人在竣工结算支付证书签发后（ ）天内仍不支付工程竣工结算价款的，承包人可以与发包人协议将该工程折价变卖。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","56",true,{"key":16,"text":17,"correct":18},"B","28",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","35","2020教材P203-204 发包人在竣工结算支付证书签发后或者在收到承包人提交的竣工结算款支付申请7天后的56天内仍未支付的，除法律另有规定外，承包人可与发包人协商将该工程折价，也可直接向人民法院申请将该工程依法拍卖。承包人应就该工程折价或拍卖的价款优先受偿。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]