[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109536,783,1,"单选题","某工程项目预付款120万元，合同约定：每月进度款按结算价的80%支付；每月支付安全文明施工费20万元；预付款从开工的第4个月起分3个月等额扣回，开工后前6个月结算价如下表，则第5个月应支付的款项为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","136",false,{"key":16,"text":17,"correct":14},"B","160",{"key":19,"text":20,"correct":21},"C","156",true,{"key":23,"text":24,"correct":14},"D","152","第5个月应支付的款项=220×80%+20-40=156万元",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]