[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109535":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109535,783,1,"单选题","某包工包料工程合同总金额为1000万元，工程预付款的比例为20％，主要材料、构件所占比重为50％，按起扣点基本计算公式，则工程累计完成至（ ）万元时应开始扣回工程预付款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","600",true,{"key":16,"text":17,"correct":18},"B","640",false,{"key":20,"text":21,"correct":18},"C","500",{"key":23,"text":24,"correct":18},"D","540","预付款=1000×20%=200万元 起扣点=1000-200\u002F50%=600万元",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]