[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109532":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109532,783,1,"单选题","承包人应在( )向发包人提交预付款支付申请。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","签订合同时",false,{"key":16,"text":17,"correct":18},"B","签订合同后",true,{"key":20,"text":21,"correct":14},"C","中标后",{"key":23,"text":24,"correct":14},"D","开工时","2020教材P194-195 承包人应在签订合同或向发包人提供与预付款等额的预付款保函后向发包人提交预付款支付申请。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]