[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109519":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1109519,783,1,"单选题","某项目合同履行过程中，由于法规变更，导致承包人成本增加，工程匀速施工没有出现进度偏差。下列关于承包人补偿的说法中，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人应给予承包人补偿",true,{"key":16,"text":17,"correct":18},"B","发包人不给予承包人补偿",false,{"key":20,"text":21,"correct":18},"C","竣工结算时，承包人与发包人协商是否补偿",{"key":23,"text":24,"correct":18},"D","通过仲裁决定是否给予承包人补偿","2020教材P178-184 法律改变引起的索赔。如果在基准日期(招标工程以投标截止日期前的28 天、非招标工程以合同签订前28 天)以后，由于发包人国家或地方的任何法规、法令、政令或其他法律或规章发生了变更，导致了承包人成本增加。对承包人由此增加的开支，发包人应予补偿。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]