[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109518":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1109518,783,1,"单选题","由于发包人的原因导致承包人自有的设备窝工，该窝工费应按照（）计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","台班费",false,{"key":16,"text":17,"correct":18},"B","台班折旧费",true,{"key":20,"text":21,"correct":14},"C","实际租金和调进调出费的分摊",{"key":23,"text":24,"correct":14},"D","设备使用费","2020教材P184-190 由于发包人或监理工程师原因导致机械窝工费的计算，如系租赁设备，一般按实际租金和调进调出费的分摊计算；如系承包人自有设备，一般按台班折旧费计算，而不能按台班费计算，因台班费中包括了设备使用费。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]