[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109512,783,1,"单选题","下列承包人因工程变更提出的调整措施项目费的事项中，需采用承包人报价浮动率计算的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安全文明施工费",false,{"key":16,"text":17,"correct":14},"B","按单价计算的措施项目费",{"key":19,"text":20,"correct":21},"C","按总价计算的措施项目费",true,{"key":23,"text":24,"correct":14},"D","实施方案未提交发包人确认的措施项目费","",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]