[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109506":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109506,783,1,"单选题","某招标工程发生工程变更，引起已标价工程量清单项目发生变化，若该项目没有适用也没有类似于变更工程项目，发承包双方参考报价浮动率进行工程项目调整。该项目中标价为3000万元，招标控制价为3300万元，施工图预算为3100万元，标底为3050万元。则承包人报价浮动率是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1.64％",false,{"key":16,"text":17,"correct":14},"B","3.22％",{"key":19,"text":20,"correct":14},"C","6.06％",{"key":22,"text":23,"correct":24},"D","9.09％",true,"2020教材P175-178 承包人报价浮动率L=(1-中标价／招标控制价)×100％=1-3000／3300=9．09％。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]