[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109504,783,1,"单选题","已标价工程量清单中有适用于变更工程项目的，采用该项目的单价；但当工程量增加( )以上时，其增加部分的工程量的综合单价应予( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10%，调低",false,{"key":16,"text":17,"correct":14},"B","10%，调高",{"key":19,"text":20,"correct":21},"C","15%，调低",true,{"key":23,"text":24,"correct":14},"D","15%，调高","2020教材P175-178 已标价工程量清单中有适用于变更工程项目的，采用该项目的单价；但当工程变更导致该清单项目的工程数量发生变化，且工程量偏差超过15% 。此时，调整的原则为：当工程量增加15% 以上时，其增加部分的工程量的综合单价应予调低；当工程量减少15% 以上时，减少后剩余部分的工程量的综合单价应予调高。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]