[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109501":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109501,783,1,"单选题","施工合同中约定，承包人承担的钢筋价格风险幅度为±5%，超出部份依据《建设工程工程量清单规范》(GB50500-2013)造价信息法调差。已知承包人投标价格、基准期发布价格分别为2400元\u002Ft、 2200元\u002Ft，2015年12月、2016年7月的造价信息发布价为2000元\u002Ft、2600元\u002Ft。则该两月钢筋的实际结算价格应分别为()元\u002Ft。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2280,2520",false,{"key":16,"text":17,"correct":14},"B","2310,2690",{"key":19,"text":20,"correct":21},"C","2310,2480",true,{"key":23,"text":24,"correct":14},"D","2280,2480","投标单价高于基准价，2015 年12 月造价信息发布价降低，按基准价算2000÷2200-1=-9.1%，超过5%，应予调整。 2400-[2200×(1-5%)-2000]=2400-90=2310(元) 投标单价高于基准价，2016 年7 月的造价信息发布价上涨，按投标单价算2600÷2400-1=8.33%，超过5%，应予调整。 2400+[2600-2400×(1+5%)]=2400+80=2480(元)",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]