[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109500":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109500,783,1,"单选题","施工过程中，出现施工图纸变更导致项目特征与招标工程量清单项目特征描述不符时，综合单价的确定应以()的项目特征为准。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","原设计图纸所示",false,{"key":16,"text":17,"correct":14},"B","清单描述",{"key":19,"text":20,"correct":21},"C","变更图纸所示",true,{"key":23,"text":24,"correct":14},"D","标准图集描述","⑴发包人在招标工程量清单中对项目特征的描述，应被认为是准确和全面的，并且与实际施工要求相符合。承包人应按照发包人提供的招标工程量清单，根据其项目特征描述的内容及有关要求实施合同工程，直到项目被改变为止。 ⑵承包人应按照发包人提供的设计图纸实施工程合同，若在合同履行期间出现设计图纸(含设计变更)与招标工程量清单任一项目的特征描述不符，且该变化引起该项目的工程造价增减变化的，应按照实际施工的项目特征，按规范中工程变更相关条款的规定重新确定相应工程量清单项目的综合单价，并调整合同价款。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]