[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109499,783,1,"单选题","某招标工程项目执行《建设工程工程量清单计价规范》（GB50500－2013），招标工程量清单中某分项工程的工程量为1500m3，施工中由于设计变更调增为1900m3，该分项工程最高投标限价综合单价为40元\u002Fm3，投标报价为47元\u002Fm3，则该分项工程的结算价为（ ）元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","87400",false,{"key":16,"text":17,"correct":14},"B","88900",{"key":19,"text":20,"correct":21},"C","89125",true,{"key":23,"text":24,"correct":14},"D","89300","本题考查的是工程量偏差。40×（1＋15%）＝46元\u002Fm3＜47元\u002Fm3。所以结算款为：1500×（1＋15%）×47＋[1900－1500×（1＋15%）]×46＝89125元。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]