[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109498":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1109498,783,1,"单选题","某土方工程招标工程量清单中，土方开挖工程量为600m3。施工过程中，由于设计变更，减少土方开挖工程量100m3，则减少后剩余部分的工程量综合单价应()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由发包人确定",false,{"key":16,"text":17,"correct":14},"B","直接采用该项目综合单价",{"key":19,"text":20,"correct":14},"C","相应调低",{"key":22,"text":23,"correct":24},"D","相应调高",true,"",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]