[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1109491":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1109491,783,1,"单选题","某独立土方工程，招标文件中估计工程量为1 万m3,合同中约定土方工程单价为20 元\u002Fm3，当实际工程量超过估计工程量10%时，需要调整单价，单价调为18 元\u002Fm3。该工程结算时实际完成土方工程量为1.2 万m3，则土方工程款为()万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","21.6",false,{"key":16,"text":17,"correct":14},"B","23.6",{"key":19,"text":20,"correct":21},"C","23.8",true,{"key":23,"text":24,"correct":14},"D","24.0","1×(1+10%)×20+[1.2-1×(1+10%)]×18=23.8（万元）",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（土木建筑）","建筑工程",0]